Yantai–Weihai UHV project Commissioned in Shandong
Yantai–Weihai UHV project commissioned
Oct 10
CCTV reports the October 10 completion and commissioning of the Yantai–Weihai 1,000-kilovolt UHV transmission project, described as the first UHV AC transmission and transformation project commissioned during the 15th Five-Year Plan. The bulletin gives a 1,197-kilometer line and says the project will transmit nuclear electricity from Haiyang, Laiyang and other Yantai areas to expand Shandong's green-power supply. The future supply benefit is the report's expectation.
The Yantai–Weihai 1,000-kilovolt UHV transmission project was completed and commissioned on October 10. CCTV calls it the first UHV AC transmission-and-transformation project commissioned during China's 15th Five-Year Plan and reports a 1,197-kilometer line. It is intended to transmit nuclear electricity from Haiyang, Laiyang and other Yantai areas and expand Shandong's green-power supply; that benefit remains prospective.
Comments 0